The external facade cladding and windows are progressing well which in about 1 month will allow the outside access scaffold to be removed.
Internally all the mechanical and electrical installations are complete to allow internal partitions to be closed up and plastered. Decorations have commenced in readiness of the science lab furniture to be installed from next week. Plans are in place to “re model” the link corridors in the existing school and to liven up the new electrical & mechanical supplies once the school is closed for the summer holidays next week.